Midtown Tampa Development – Tampa, FL

MidTown Tampa is a new 1.8 million-SF hotel-retail-office-housing development located in the WestShore District. Once complete, the complex will include approximately 240,000-SF of retail and entertainment space; 186,000-SF of Class A office space; 400 condos and/or apartments and a 225-room boutique hotel.

Currently, Barr & Barr’s scope of work includes:

  • All underground site utilities and building pads, final landscaping and hardscaping for the entire 22-acre site.
  • Offsite work includes: Additional roadway signalization and turn lanes, repaving and milling asphalt, striping, all work in public roadways – $10 million.
  • West Office Tower: Core & Shell construction of 186,000-SF, eight-stories and $32 million. Includes pedestrian bridge connecting to parking deck, plus first floor retail space (REI, sundries store, etc.) and lobby.
  • Megadeck Parking Garage: Stand-alone deck, six-stories and 350,000-SF including approximately 1,100 spaces, $17.5 million.
  • Whole Foods Grocery Shell & five-story parking garage: Whole Foods store is 55,000-SF, Parking garage which will be built above the grocery space is five-stories, approximately 350,000-SF and 750-spaces.

Management of entire site throughout the multi-year life of the project including all facilities such as office, retail, hotel, and multi-family.

Facts

Size:186,000 SF (Office Building)

Schedule:Multiple durations: West Office Tower – 19 Months Whole Foods & Parking Garage – 14 Months Megadeck Parking Garage – 12 Months

Construction Type:Construction Manager-at-Risk

Owner:Bromley Companies

Architect:Multiple: TVS Design (Office Building), WDG Architects (Whole Foods) and Finfrock (Megadeck Parking Garage)